Step 7: Put communication board back to the unit.
Step 8: Put wire cover back to the unit. Now the inverter is providing parallel operation
function.
4. Mounting the Unit
When installing multiple units, please follow below chart.
500mm 500mm 500mm 500mm500mm
500mm
500mm
NOTE: For proper air circulation to dissipate heat, allow a clearance of approx. 50 cm to the
side and approx. 50 cm above and below the unit. Be sure to install each unit in the same level.
5. Battery Connection
WARNING! Be sure that all inverters will share the same sets of batteries. Otherwise, the
inverters will transfer to fault mode.
WARNING: Be sure the length of all battery cables is the same. Otherwise, there will be
voltage difference between inverter and battery to cause parallel inverters not working.
Follow below chart to connect batteries. All battery cables are connected from inverters to
batteries via the same BUS bar.